Cable Pulling and Electrical Installations
This project showcases Banneen’s expertise in delivering comprehensive electrical installation solutions for one of ARAMCO’s key facilities at the Tanajib Gas Plant. The scope of work included cable pulling for low, medium, and high voltage systems, which required precision and adherence to strict safety standards. These cables formed the backbone of the plant’s power distribution network, ensuring reliable and efficient energy flow to critical operations.
The project also involved the installation of panel boards and termination of transformers, which are essential components for regulating and distributing electrical power. Banneen’s team ensured that all installations adhered to IEC (International Electrotechnical Commission) and NEC (National Electrical Code) standards, guaranteeing safety, reliability, and compliance with industry best practices.
Additionally, the project included the installation of lighting poles and fixtures, providing energy-efficient lighting solutions for the facility. This included the use of advanced LED technology, ensuring long-term cost savings and reduced environmental impact. The lighting system was designed to meet ARAMCO’s stringent operational requirements, offering optimal illumination for both indoor and outdoor spaces.
Scope Of Work
- Cable Pulling Low & Meduim Voltage
- Insstallation For Panel Board And Termentation For Transformar
- Insttallation For Lightining Pole And Lighting Fixture
Our Latest Work
CLIENT
ARAMCO
LOCATION
Tanajib Gas Plant / TCF
Contract Value
5,150,000 SAR
Status
Completed
Scope
Cable pulling (low and medium voltage), panel board installation, transformer termination, lighting pole and fixture installation.
Key Features
Technical Highlights and Specialized Solutions Delivered